Case Study

Cadland Estate

Anesco worked with the Cadland Estate in the New Forest to develop a model for sustainable farming.
All Case Studies

Project results:

Yearly CO2 Savings:

2,797 Tonnes

Generating enough renewable energy to power:

1,700 homes

Project Outline:

This included the development of a 5MWp solar farm. Constructed on grazing used to grow potato crops, the scheme is capable of generating enough electricity to power around 1,700 homes.

The solar farm has been completed as part of a 25 year land lease agreement and will be maintained and monitored by Anesco through its unique AnescoMeter service.

  • System size: 5MWp
  • Area covering: 30 acres
  • Number of panels: 18,000 solar PV panels
  • Length of frames: 9 kilometres
  • Number of groundscrews: 5,000
  • Construction time: 13 weeks
  • Project Lifetime: 25 years
  • Yearly CO2 Savings: 2,797 tonnes

Got questions about this case study?

Call our team of experts on 0845 894 4444.

Our Customers

Commercial

Local Government

Housing Associations

Homeowners

This is what we do.

We are first to understand new technologies and to introduce commercial models that enable our customers to improve their energy usage and save money, while tackling the world’s carbon emissions. With our global approach to innovation and world-class delivery we are driving the energy efficiency sector forward.